Introduction
A major OEM faced delays in New Product Development (NPD) due to incomplete PPAP (Production Part Approval Process) submissions from Tier-1 and Tier-2 suppliers. With on-time PPAP completion rates as low as 30-40%, Catalydd intervened to streamline documentation, address skill gaps, and ensure compliance with OEM’s Level 3 PPAP requirements.
Challenges
- Pending PPAP Submissions: Critical documents delayed at NPD stage.
- OEM Requirements: Level 3 PPAP (PSW, product samples, supporting data) not met.
- Skill Shortages: Suppliers lacked expertise to prepare PPAP/Re-PPAP documentation.
- Low On-Time Completion: Only 30-40% of PPAPs submitted monthly met deadlines.
Project Milestones
- Roadmap Development (Month 1): Collaborated with OEM to define PPAP completion targets.
- Commodity-Specific Deployment (Month 1-2): Assigned expert engineers (Sheet Metal, Casting, Machining, etc.) to suppliers.
- Execution & Review (Month 2-4): Weekly/Monthly progress tracking and issue resolution.
- Final Submission (Month 5): Completed pending PPAPs and uploaded documents to OEM portals/SAP.
Our Solution
Catalydd’s multi-pronged approach included:
- Commodity Expertise: Deployed specialists for Sheet Metal, Casting, Machining, Hydraulics, and Surface Treatment to address technical gaps.
- Documentation Support:
● Prepared PSW (Part Submission Warrant), dimensional reports, and process flow diagrams.
● Compiled supporting data (material certifications, process validations).
- Training: Upskill supplier teams on PPAP requirements and portal submissions.
- Sustained Monitoring: Regular audits to ensure adherence to timelines and quality standards.
Results
- 90% On-Time PPAP Completion: Surpassed OEM’s submission deadlines.
- Reduced NPD Delays: Accelerated product launches by resolving documentation bottlenecks.
- Supplier Empowerment: Enhanced in-house capability to manage future PPAP/Re-PPAP activities.